Flagstone Logistics Estate Community Page

 

Charter Hall is one of Australia’s largest owners of industrial and logistics property.

Our vision for Flagstone Logistics Estate is to deliver one of the most sustainable business precincts in Australia that will bring new businesses, services and jobs to the Logan community.

The 100-hectare estate on the corner of Mount Lindesay Highway and Crowson Lane in North Maclean is part of the Greater Flagstone Priority Development Area.  

Initial stages of Flagstone Logistics Estate are complete and operating. Ultimately, the estate will be home to dozens of businesses in warehouses ranging from 10,000 to 100,000 square meters. Open space areas, off-road paths and other amenities will make the site a vibrant, sustainable precinct.

Access to the estate is via Mount Lindesay Highway, with a service road directly off the highway roundabout.

Planning timeline

’10
October: The Urban Land Development Authority (ULDA) declared the Greater Flagstone Priority Development Area (PDA)
’16
February: The Department of the Environment (Australian Government) issued a conditional approval over the land to clear vegetation 
’21
September: Economic Development Queensland (EDQ) approved a PDA Development Application over the land. The conditional approval for reconfiguring a lot (ROL) included:
- Earthworks to amend the site levels
- Road layouts and site access arrangements 
- Civil servicing arrangements 
’22

January: Charter Hall acquired the land

July: Site clearing works commenced

’23

August: Bulk earthworks commenced

September: EDQ approved a Change to PDA Development Approval (ROL)

’24

March: EDQ approved a Change to a PDA Development Approval (ROL)

October: EDQ approved Warehouse 1 (Material Change of Use for Warehouse - Distribution Centre) 

’25

March: EDQ approved
- a Change to a PDA Development Approval (ROL)
- Warehouse 2 (Material Change of Use for Warehouse - Distribution Centre)

May: EDQ approved Warehouse 3 (Material Change of Use for Warehouse - Distribution Centre) 

August: EDQ approved Warehouses 4 & 5 (Material Change of Use for Warehouse - Distribution Centre) 

Construction update

2021

PDA Development Permit Granted

2022

Clearing works commenced 

2023

Bulk earthworks commenced 

2024

Completion of bulk earthworks

Roadworks and services installation commenced

First warehouse commenced

2026

Third warehouse commenced

2025

Completion of roadworks and services for Stage 1, with Stage 2 underway

First warehouse complete and operational

Second warehouse commenced

Bulk Earthworks:

Completed


Stage 1 to 3 Roadworks:

Commenced August 2024

  • Stage 1 works complete
  • Target completion of Stage 2 works December 2026 (pending weather and construction conditions)
  • Target completion of Stage 3 works December 2027 (pending weather and construction conditions)


Building Phase Works: 

Ongoing until completion of the estate

Noise

Contractors working on the site will be asked to manage construction noise throughout the project duration. This includes: 

  • Regular updates to the community on planned noisy works
  • Monitoring noise levels where required
  • Ensuring construction methodology minimises intensive activities 

Works are to only take place within the approved construction hours of 6.30am to 6.30pm Monday to Saturday. Any work outside of these hours is subject to EDQ Approval. 

 

Dust

To minimise the impact of dust, contactors working on the site will be required to cover or vegetate exposed surfaces as soon as practicable. When not possible, exposed surfaces are to be wetted down or treated so as to prevent dust. Construction access points are to be well maintained and swept, ensuring tracking of dirt and dust onto the road network is minimised. 

 

Year 3 Audit Report

Year 2 Audit Report

Year 1 Audit Report

Stormwater Management Plan

Offset Management Plan

Staging Plan

Plan of Reconfiguration

Bulk Earthworks Plan

Charter Hall is committed to an ongoing, open dialogue with the local community and take all feedback seriously.

We will arrange to distribute updates to residents and businesses in surrounding streets of the site one week ahead of any major activities which may affect traffic, access or other local conditions. If you would like to be added to the mailing list for these notices or ask us any questions, please email us at the below address: 

Contact

Flagstone Community Contact

Flagstone Community Contact